Project Duration: 48 months
Progress52%
WP1
Project Coordination, Quality Assurance and Risk Management
Project Coordination, Quality Assurance and Risk Management
Duration: M1-M48
Leader: CETEC
Leader: CETEC
Progress50%
WP2
Enzymatic biodegradation of PET to obtain terephthalic acid and ethylene glycol
Enzymatic biodegradation of PET to obtain terephthalic acid and ethylene glycol
Duration: M1-M36
Leader: ECS
Leader: ECS
Progress63%
WP3
Enzymatic biodegradation of PE to obtain alkanes
Enzymatic biodegradation of PE to obtain alkanes
Duration: M1-M24
Leader: UG
Leader: UG
Progress51%
WP4
PHBV range production
PHBV range production
Duration: M1-M44
Leader: UA
Leader: UA
Progress21%
WP5
PHBV compounding and transformation into food and drink packaging
PHBV compounding and transformation into food and drink packaging
Duration: M1-M48
Leader: CETEC
Leader: CETEC
Progress2%
WP6
Food & drink packaging from upPE-T technologies validation in a real environment
Food & drink packaging from upPE-T technologies validation in a real environment
Duration: M1-M248
Leader: TECN
Leader: TECN
Progress1%
WP7
Project sustainability assurance
Project sustainability assurance
Duration: M1-M48
Leader: IDI
Leader: IDI
Progress41%
WP8
Project Standardization activities, Certification schemes & Exploitation
Project Standardization activities, Certification schemes & Exploitation
Duration: M1-M48
Leader: UNE
Leader: UNE
Progress37%
WP9
Project dissemination, communication, and European Citizens Awareness
Project dissemination, communication, and European Citizens Awareness
Duration: M1-M48
Leader: MoNS
Leader: MoNS
Progress43%